Archive for the ‘Projects’ Category

The tile goes in

Sunday, October 29th, 2006

This weekend the rest of the copping was installed. Too many pieces of the copping were damages to finish the outside ring on the spa. They had to order more, and they should be here by tuesday.

The tile went in this weekend. It’s amazing how good it looks.

DSC01268.JPG

You can see how it looks around the skimmer with the copping

DSC01269.JPG

Tomorrow they will start installing the outside form for the spa, so we can extend the copping and attach the tile.

Again, I am dealing with a flakey company. We are trying to get a bid on the pavers, but the company we are working with has not provided us with a quote . They have until monday or we start looking for a new company.

You can leave your hat on.

Thursday, October 26th, 2006

Now that all the heavy stuff is done, the coping is being installed. Because our pool is so curvy, it is hard to see how it will look until the grout is installed.

DSC01265.JPG

They should finish the coping cap today, and be able to start on the tile tomorrow. That assumes the materials arrive today 😉

Work starts up again.

Monday, October 23rd, 2006

Well after rain last week and some delays due to scheduling we are back working on the pool.

The trenches are all filled in, except for one small section. While digging up the dirt, we this funky connection.

DSC01261.JPG

Nothing we have found underground has made any sense. This is why we are ripping out everything and starting from scratch.

The new skimmer was set in concrete today.

DSC01262.JPG

And the coping stones arrived today as well.

DSC01263.JPG

Tomorrow they will start preparing the edge of the pool to install the coping. Things should start moving along again.

knock three times on the pipes

Friday, October 13th, 2006

The last two weeks have been spent pretty much tearing out concrete. The company did a really piss-poor job. It was supposed to take them 2.5 days and it took almost ten, yes 10 days. Now, yes the concrete was thicker than they planned, but I don’t by that excuse. They should have brought out more crew to get it done on time.

After they were done, we dug trenches. These trenches will hold the water, electrical, gas and my network conduit. It will be nice to have all this under ground.

DSC01254.JPG

We also upgraded all the plumbing to bigger pipes. One of the problems with the old system is the pipes were too small, so the volume of water was not large enough to produce the bubbles for the spa.

DSC01256.JPG

We installed a new suction line so that the skimmer and suction are separate. The should help prevent the pump from ever running dry. In addition, we added a new check valve to the solar return. This helps eliminate a dangerous valve that was in the system that could be closed and build up pressure. We removed this and replaced it with a check valve.

All of the equipment was moved down about five feet. so that it is away from the doorways. This will allow us to put our trash containers outside the doors and give us more room for the walkway.

At the end of this week, they finally filled in all the trenches. Just in time too, as it started to rain today. This weekend will be spent pulling the cables through the data pipes and hooking up the network and cable-tv underground. If time permits, I will work on clearing out dirt to start leveling the hill. I plan to terrace it to two levels.

Tear down the waterfall!

Thursday, September 28th, 2006

Ok, as most of you know I have been unhappy with the waterfall in my back yard since the day it was install. I finally decided to tear it out and start all over.

They started by taking down all the rocks and diverting the transition stream. When they took up the liner they found several holes. This is where all my water has been seeping out. I am glad after almost 4 years we got to the bottom (pun intended) of it.

DSC01193.JPG

With the stream diverted, we now have a good area where the foot bridge will cross and I can put a bridge there for my trains. I am amazingly pleased with how well it came out.

DSC01200.JPG

At the end of the 1st day, they completed the bottom half of the new waterfall. The new waterfall will be more of a terraced drop instead of a cascade. This will give it a nice look. I plan to have two bridges that run over the falls. I just have to figure out how much space I will have.

DSC01203.JPG